  • Question 1
    • A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was
      appointed to attend the first meeting with the auditors scheduled for the following week.
      What should the project manager do to prepare for the audit?

      Answer: B
  • Question 2
    • Midway through the execution of an agile project, there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?

      Answer: D
  • Question 3
    • A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource
      for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a
      leave.
      What should the project manager do next?

      Answer: C
  • Question 4
    • A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.
      Which estimation technique should the project manager recommend?

      Answer: C
  • Question 5
    • A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.
      What immediate corrective action should the project manager take?

      Answer: A