×

Special Offer! November Sale at DumpsCity! Get 20% Off on All Certification Exam Questions. Use Code: DC20OFF

Free PMI PMP Exam Questions

Try our Free Demo Practice Tests for Comprehensive PMP Exam Preparation

  • PMI PMP Exam Questions
  • Provided By: PMI
  • Exam: Project Management Professional (2022 Version)
  • Certification: PMI PMP
  • Total Questions: 1808
  • Updated On: Nov 14, 2024
  • Rated: 4.9 |
  • Online Users: 3616
Page No. 1 of 362
Add To Cart
  • Question 1
    • A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?

      Answer: A
  • Question 2
    • A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
      What should the project manager do?

      Answer: D
  • Question 3
    • A product owner has provided the team with a prioritized backlog for the initial
      launch of a new product. After analysis, the team concludes that some work is missing to
      support the initial launch and provides this information to the product owner. The product
      owner acknowledges the missing work and adds it to the bottom of the backlog. The team is
      not happy with the prioritization that the missing work received.
      What should the project manager do in this situation?

      Answer: D
  • Question 4
    • A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?


      Answer: D
  • Question 5
    • A company's key product is evolving and requires the use of a new technology. No one on the team is familiar with this technology; however, experienced developers on the team volunteered to study the concepts and application and believe they will be able to take full responsibility for the new technology.
      What should the project manager do?

      Answer: B
PAGE: 1 - 362
Add To Cart

© Copyrights Dumpscity 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the Dumpscity.