×

Special Offer! November Sale at DumpsCity! Get 20% Off on All Certification Exam Questions. Use Code: DC20OFF

Free PMI PMI-SP Exam Questions

Try our Free Demo Practice Tests for Comprehensive PMI-SP Exam Preparation

  • PMI PMI-SP Exam Questions
  • Provided By: PMI
  • Exam: PMI Scheduling Professional
  • Certification: PMI SP
  • Total Questions: 325
  • Updated On: Nov 20, 2024
  • Rated: 4.9 |
  • Online Users: 650
Page No. 1 of 65
Add To Cart
  • Question 1
    • You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed? 

      Answer: C
  • Question 2
    • John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

      3

      Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days? 

      Answer: A
  • Question 3
    • Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three. 

      Answer: B,C,D
  • Question 4
    • You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?  

      Answer: B
  • Question 5
    • If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project? 

      Answer: A
PAGE: 1 - 65
Add To Cart

© Copyrights Dumpscity 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the Dumpscity.