×

Special Offer! Limited-Time Offer! Get 25% Off on All Certification Exams – Prepare & Pass with Confidence! Use Code:  DC25OFF  

Free PMI PMI-SP Exam Questions

Try our Free Demo Practice Tests for Comprehensive PMI-SP Exam Preparation

  • PMI PMI-SP Exam Questions
  • Provided By: PMI
  • Exam: PMI Scheduling Professional
  • Certification: PMI SP
  • Total Questions: 325
  • Updated On: Mar 26, 2025
  • Rated: 4.9 |
  • Online Users: 650
Page No. 1 of 65
Add To Cart
  • Question 1
    • John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

      Answer: D
  • Question 2
    • Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

      Answer: B
  • Question 3
    • You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario? 

      Answer: A
  • Question 4
    • Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

      Answer: D
  • Question 5
    • You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index? 

      Answer: C
PAGE: 1 - 65
Add To Cart

© Copyrights Dumpscity 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the Dumpscity.