×

Special Offer! November Sale at DumpsCity! Get 20% Off on All Certification Exam Questions. Use Code: DC20OFF

Free PMI PMI-CP Exam Questions

Try our Free Demo Practice Tests for Comprehensive PMI-CP Exam Preparation

  • PMI PMI-CP Exam Questions
  • Provided By: PMI
  • Exam: Construction Professional in Built Environment Projects
  • Certification: PMI Built Environment
  • Total Questions: 60
  • Updated On: Nov 11, 2024
  • Rated: 4.9 |
  • Online Users: 120
Page No. 1 of 12
Add To Cart
  • Question 1
    • During the commissioning and startup of a built environment project, two interface stakeholders disagree about their involvement in a recent work incident, accusing each other of dodging responsibility. To avoid such an issue in the future, the construction professional decides to include a RACI matrix in the Interface Agreement (IA). RACI is an acronym for:

      Answer: D
  • Question 2
    • An organization is running a construction megaproject with over 100 interfaces. As it faced some issues in IM implementation, the organization requested the advice of a senior construction professional. After assessing the existing IM implementation, the construction professional recommended the organization to set up a single centralized document to easily review the status of all Interface Agreements (IA).

      What document does the construction professional refer to?


      Answer: C
  • Question 3
    • A construction professional is in charge of building a hospital. Knowing that the project includes a diverse group of stakeholders, the construction professional opted for using a project management information system (PMIS) to increase collaboration and decision-making. Yet, a key stakeholder prefers to receive some important documents on paper to be manually processed and approved.

      What should the construction professional do in this case?


      Answer: A
  • Question 4
    • A construction professional decides to use the PDRI tool throughout the Front End Planning (FEP) process. The construction professional defined four assessment points: after the feasibility study, after the concept phase, during the detailed scope phase, and at the end of the FEP phase.

      How will the PDRI score typically evolve through these assessment points?


      Answer: B
  • Question 5
    • Before taking a long leave, a construction professional informed the person filling in for them that they should regularly calculate the project’s Earned Value (EV). Among the following options, what is the right description of an Earned Value?

      Answer: C
PAGE: 1 - 12
Add To Cart

© Copyrights Dumpscity 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the Dumpscity.