Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product
manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to
produce release?